Liquid filled Transformers

October 28, 2002

Sponsored by:

grf_infraspection_institue
iiRealw1
Liquid filled Transformers

A thorough infrared inspection of an electrical transformer can point out symptoms of loose connections as well as other possible problems. When performing an infrared inspection of a liquid-filled transformer, be certain to include not only the primary and secondary connections but also the following items as well:

1) Inspect neutral and grounding connections for hot spots.

2) For transformers with separate tanks for each phase, compare phase tanks to each other. Transformers with balanced loads will exhibit similar temperatures between tanks.

3) Qualitatively inspect radiator section. Radiator tubes should be uniform in temperature and, in most cases, should operate above ambient temperature.

4) Compare transformer operating temperature to nameplate rating. For long term service, transformers should not operate above their maximum rated temperature.

5) Compare tap changer tank to main body of transformer. For properly operating tap changers, tap changer tank should not appear warmer than main body of transformer.

In conjunction with the infrared inspection, cooling fans and or pumps should be checked for proper settings and operation.

Finally, transformers require proper air circulation for cooling. To help ensure maximum airflow, transformer radiators should be unobstructed and free from dirt and debris.

Advertisement

Latest Tips

IR Inspections of Emergency Power Systems

December 16, 2024

Temperature Differentials for Infrared Building Inspections – Part 2

December 09, 2024

Temperature Differentials for Infrared Building Inspections – Part 1

December 02, 2024

Thanksgiving Safety Tip

November 25, 2024

Gauging When IR Inspection Window Opens/Closes

November 18, 2024